All case studies
Toyota Motor Corporation

Supply chain risk

Toyota: secure backup supply

Line up checked backup supply for the category manager’s decision before parts run short.

By OneShot · Updated

first-tier suppliers Toyota works with
11,000+tier 2 and tier 3 suppliers behind them also register in RESCUE
all Japan lines halted, Feb 8 to 13
6 daysa month after one steel supplier's January 8 blast
all Japan lines running after Kyushu quakes
May 6after almost all lines stopped in stages from April 18

About Toyota Motor Corporation

Toyota Motor Corporation builds vehicles on assembly lines across Japan and keeps supplier data for disasters in its RESCUE database.

supply chain items stored in RESCUE
6,800
disaster that led to building RESCUE
2011
  • Apr 25-28most Japan lines restarted

    One island's parts, almost every line

    Parts shortages from the Kyushu earthquakes stopped lines in stages April 18 to 23, and ongoing tremors kept every plan subject to change.

    • Alternate line plan
    • Other steelmakers' supply
    • Production restart notice

    One steel supplier, every Japan line

    An explosion at one steel supplier stopped all Japan lines until alternate lines and other steelmakers stepped in with backup supply.

  • Jan 8plants run on parts stocked outside Noto

    Noto: many local suppliers hit

    The Noto Peninsula earthquake of January 1, 2024 hit many local suppliers and affiliates, and aftershocks left operations after January 15 undecided.

What Toyota Motor Corporation has published 7 sources

In April 2016 Toyota announced that parts shortages caused by the severe earthquakes on Japan’s island of Kyushu would suspend production on almost all of its vehicle assembly lines in Japan, in stages between April 18 and 23. Most lines restarted between April 25 and 28. After the Noto Peninsula earthquake on January 1, 2024, Toyota said many of its local suppliers and their affiliates had been affected, and that it would run its Japanese vehicle plants on parts in stock outside the affected areas.

Toyota’s 2026 Sustainability Data Book lists production halts from supply chain disruption caused by abnormal weather among its climate-related risks. It describes building a database from suppliers’ highly confidential information and training with suppliers regularly, so that supply chain information is visible before a disaster strikes. These are Toyota’s own accounts of its supply chain and its preparations. The OneShot workflow below secures backup supply before a supplier-site disruption stops a line.

The OneShot solution

Secure backup supply before a supplier-site disruption stops a line.

Starts on

The scheduled watch finds a disaster, weather or compliance event near a supplier site, or a site is added or changed.

  1. Goal

    Site watch

    Starts on
    A check every 15 minutes, and any change to supplier records.
    Does
    Maps each tier-1 and tier-2 site to parts and lines, and opens a watch item when a quake strikes nearby.
    Returns
    A watch item: event, distance, parts at stake, lines fed.
    • Supplier site and part records
    • Place Resolve
    • Legal Entity Identifier
    • Earthquakes
    2 steps
    1. Map each site to parts and lines

      Load every tier-1 site and its tier-2 sites from the supplier records, with parts, lines fed, stock cover and approved alternates. Resolve each address and confirm the legal entity; conflicts go to the category manager.

    2. Watch the ground at each site

      Every 15 minutes, check each site against earthquake data. A quake within the set distance opens a watch item with its distance, magnitude and the parts at stake.

  2. Goal

    Exposure and supplier status

    Starts on
    A watch item the site watch opens for a supplier site.
    Does
    Scores interruption risk from reports, single sourcing and stock cover, then emails the supplier and calls past the deadline.
    Returns
    A flag with parts, lines, days of cover and the supplier's answer.
    • Supplier site and part records
    • Deep Research
    • Predict
    • Email
    • Email Inbox
    • Voice call time
    2 steps
    1. Score the exposure

      Research reports on power, roads and plant damage near the site. The prediction tool scores interruption risk from the event, single sourcing and stock cover; items over the threshold become flags.

    2. Ask the supplier for status

      Email the site's contact, and the tier-1 supplier buying from a tier-2 site, for status, shipment effect and a recovery date. Call if unanswered by the deadline; silence stays unconfirmed.

  3. Goal

    Backup supply

    Starts on
    A flag whose supplier has not yet confirmed full shipments.
    Does
    Screens makers of the same part, asks approved alternates for capacity, and proposes a volume shift for the category manager.
    Returns
    Checked options with confirmed capacity, the manager's decision, a recheck date.
    • Supplier site and part records
    • Company Find
    • Company Profile
    • Sanctions Listing (company)
    • Email
    • Email Inbox
    • Solve
    3 steps
    1. Find and check backup supply

      Search for makers of the same part with the same process, profile each one and screen it against sanctions lists for companies. Approved alternates already in the records come first.

    2. Confirm capacity with the alternates

      Email each approved alternate supplier for its spare capacity and lead time on the parts at risk, and record each answer with who gave it and when.

    3. Put the options to the category manager

      The optimization tool proposes how volume could shift across alternates within confirmed capacity and remaining stock cover. The category manager decides on the goal's private request page; decision and recheck date go on the record.

What the workflow produces

Supplier site risk record
  • Site
  • Screening
  • Disruption flag
  • Decision
Pays back
Line stoppages avoided
Decided by
Category manager for the parts the site supplies
Done when
Every flag has the supplier’s answer or a recorded non-response, checked backup options and the category manager’s decision, made before stock cover runs out.

Illustrative

One supplier site, start to finish

A magnitude 6.4 earthquake strikes at night 18 km from a tier-2 aluminum casting plant that ships four castings through two tier-1 suppliers.

  1. Agent

    Watch item opened: four castings at stake, feeding assembly lines A2, B1 and C1.

  2. Agent

    Power cuts reported nearby; 72% interruption risk, three castings single-sourced, 3.5 days of cover.

  3. Agent

    Emails the plant and both tier-1 buyers for status and a recovery date by 08:00.

  4. Agent

    The plant is silent, so a call reaches the shift manager: two cells down, no date.

  5. Agent

    Screens six casters with the same alloy and press size, then emails the two approved alternates.

  6. Outside party

    One alternate confirms bracket capacity from Thursday but has no tooling for the hinges.

  7. Decision

    The category manager takes the bracket offer, qualifies a second hinge caster, rechecks Wed 08:00.

Supplier site risk record: aluminum casting plant
Event
M6.4 quake, 18 km, Tue 02:14
Likelihood
72%, threshold 50%
Supplier answer
Partial, unconfirmed
Recheck
Wed 08:00
PartFeedsCoverSourcingBackup and decision
Front hinge castingDoor modules, A2 and B13.5 daysSingle sourceSecond caster in qualification
Rear hinge castingDoor modules, A2 and B13.5 daysSingle sourceSecond caster in qualification
Engine bracket castingEngine parts, line C13.5 daysSingle sourceAlternate from Thu, confirmed 11:20
Gearbox cover castingEngine parts, line C16 daysTwo sourcesShift volume to the second source

Where it gets hard

  • The category manager moves volume

    The agent places no orders, shifts no volume and qualifies no supplier. A sanctions name match goes to compliance first.

  • It sees what its sources cover

    Where no official alert feed covers a site's area, the watch relies on earthquake data and local reports. Unlisted tier-2 sites stay invisible.

  • It needs the supplier map

    Sites to tier 2, parts per line, stock cover and alternates are suppliers' confidential data, so access carries the same terms.

What to measure

  • Flags decided before stock cover runs out
  • Time from event to flag
  • Supplier response time
  • At-risk parts with an approved alternate

What comes next

  • Rehearse a Nankai Trough earthquake and list every site the records cannot place.
  • Widen the map to material makers, such as steelmakers behind cast and forged parts.
  • Keep each flag open until the first full shipment, recording days from the event.

The agent’s tools

  • Place Resolve
  • Legal Entity Identifier
  • Earthquakes
  • Deep Research
  • Predict
  • Email
  • Email Inbox
  • Voice call time
  • Company Find
  • Company Profile
  • Sanctions Listing (company)
  • Solve
  • Supplier site and part records

Live toolConnection to your systems

What each connection does
Supplier site and part records
Read active suppliers, each production site address, the parts it supplies, stock cover and approved alternates; record the category manager’s decision and recheck date.

Workflow pricing

Scope the full workflow around your volume, business systems and required outcome.

Discuss workflow pricing →

Bring a workflow
like this one.