Capital projects
EDF: hold Hinkley Point C to its cost and date
Forecast cost and completion as ranges, commit at the 80th percentile and recover each package that puts it at risk.
By OneShot · Updated
- completion cost, 2015 values
- £31-34bn
- earlier completion cost estimate
- £25-26bn
- power start scheduled in May 2022
- June 2027
The documented problem
In 2024 EDF raised its Hinkley Point C cost estimate and estimated a further 12-month delay would add around £1 billion.
What EDF has published 1 source
On January 23, 2024, EDF said the cost of completing Hinkley Point C was now estimated at between £31 billion and £34 billion in 2015 values, against an earlier estimate of between £25 and £26 billion. In May 2022 it had scheduled the start of electricity production for June 2027. EDF analysed three scenarios for Unit 1: operation in 2029 as the target, 2030 as the base case and 2031 if a further 12-month risk materialised.
EDF named the cost of civil engineering and the longer electromechanical phase as the two main reasons for the revision, and estimated that the further 12-month delay would add around £1 billion in 2015 values. These are EDF’s own estimates. The OneShot workflow below forecasts a capital project’s cost and completion date as ranges and carries the forecast into recovery actions.
- EDF: Hinkley Point C update, January 2024Company source
The OneShot solution
Commit to the cost and date the project meets at its 80th percentile, and recover every package that puts them at risk.
A monthly progress report, a package over its estimate or a new risk on the register.
Gather the packages
Read each work package with cost to date, remaining estimate, duration and the packages it waits on, and the risk register with each risk’s chance and impact. Flag packages whose progress report is late.
- Project schedule and cost records
Get ranges from the owners
Ask each package owner through the goal’s private request page for a low, likely and high remaining cost and duration, and the reason for any change since last month. Record who gave each range.
- Project schedule and cost records
Simulate cost and completion
The OneShot agent uses its prediction tool to run thousands of outcomes for total cost and critical-path duration, with each risk occurring or not at its stated chance. It reports the 50th and 80th percentiles and the packages that move them most.
- Predict
- Project schedule and cost records
Get the commitment approved
Give the project director the forecast, the packages driving it and the recovery options their owners propose, each run as its own case. Record the committed cost and date and the approved recovery actions for the project board.
- Project schedule and cost records
Recover and re-forecast
Give each package owner its approved action and deadline on its request page, and chase it. Re-run the forecast every month on actual progress; a committed figure at risk goes to the project director before the board meets.
- Project schedule and cost records
What the workflow produces
Project cost and schedule forecast- Packages
- Forecast
- Drivers
- Recovery
- Pays back
- Months of delay recoveredAbout £1bn if a further 12-month delay is avoided
- Decided by
- Project director, with the project board
- Done when
- The board holds a committed cost and date at the 80th percentile, and every package driving a slip has an approved recovery action with an owner.
Where a person decides
Ranges come from package owners; the agent does not set them.
Contract changes and safety decisions stay with the project director.
A forecast past the committed figure goes to the board; it does not become a new baseline on its own.
What to measure
- Forecast completion against the committed date
- Gap between the 50th and 80th percentiles
- Packages reporting late
- Months recovered by approved actions
The agent’s tools
- Predict
- Project schedule and cost records
Live toolConnection to your systems
What each connection does
- Project schedule and cost records
- Read work packages with cost to date, remaining estimate, duration and dependencies, and the risk register; record the committed estimate and recovery actions.